Net Meter Shortage Stalls Rooftop Solar Installations Across Telangana
Rooftop solar installations across Telangana are facing delays due to a shortage of three-phase net meters, leaving several completed solar power systems unable to connect to the electricity grid.
Solar vendors have reportedly been making repeated visits to distribution company offices to obtain meters, while several installed rooftop solar systems remain idle. The delay is affecting consumers and solar developers financially, as completed installations cannot begin supplying electricity to the grid.
The shortage has resurfaced after limited stocks of three-phase net meters were exhausted. Around 2,000 pending meter requirements were cleared following subsequent supplies, but the availability of three-phase meters has once again become a concern.
Officials of Telangana Southern Power Distribution Company Limited (TGSPDCL) stated that 8,900 single-phase net meters are currently available, while another 4,000 meters are expected to arrive after Diwali.
According to TGSPDCL, the supply disruption is linked to a global shortage of electronic printed circuit board (PCB) components, which has affected manufacturers’ ability to meet delivery schedules. The utility had earlier placed orders for 15,000 net meters, of which 7,000 were received in August.
The shortage is affecting residential, commercial and industrial rooftop solar installations across the state.
Burra Ashok Kumar Goud, President of the Telangana Solar Energy Association, highlighted that consumer interest in rooftop solar remains strong, but delays in meter availability are preventing completed projects from becoming operational.
The situation highlights the importance of timely metering infrastructure in supporting rooftop solar adoption and ensuring effective grid integration of distributed renewable energy.